HUB North Shore Committee meeting May 2, 2024
General
 
Agenda additions
 
Introductions
 
Public Input/Consultations
 
Public input is critical when Council and Staff make trade-offs and decisions. Please make sure your voice is heard!!
 
   
  +
Attending; Paul J (chair), Peter, Fiona, Finn (online) Erika, Mike, Kira
   
Goals & Objectives
 
2024 Goals
 
Presentation with maps and list of gaps on our priority bikeways
 
Next priority Bikeways - current Gaps Map
 
Recruiting - Fill vacant positions(click for details)
 
CNV Liaisons
 
Events coordinator
 
More details and roles on see HUB resource page
 
Ensure Cycling Priorities are in DWV's Transportation Strategy
 
   
 
General
 
Agenda additions - none
   
 
Events
 
Events
 
Earth Day event - CNV - was held Sat, April 20th in Moodyville Park.
Need a coordinator/organizer for Events
 
 
Thanks to Blake, Erika, Finn, Kira, Derrick & Cathy for making this event a success.
Earth Day event - CNV - Sat, April 20th in Moodyville Park.
 
  +
Thanks to Blake, Erika, Finn, Kira, Derrick & Cathy
 
 
1st annual Bike Festival - City hall Plaza, June 1st
 
1st annual Bike Festival - City hall Plaza, June 1st
 
Sponsored by DNV, CNV, ICBC & North Shore Safety Council
 
Sponsored by DNV, CNV, ICBC & North Shore Safety Council
Line 27: Line 17:
 
12-2pm:
 
12-2pm:
 
Can't: Don, Paul J, Duncan
 
Can't: Don, Paul J, Duncan
  +
There is confusion as to wether this station is part of GBBW. Paul J has contacted An Hoang for clarification.
  +
  +
 
Spring Go By Bike Week, June 3-9, 2024.
 
Spring Go By Bike Week, June 3-9, 2024.
 
Celebrations stations (2 per station):
 
Celebrations stations (2 per station):
 
Mon, June 3, 4-6pm:, 13th & Argyle (Ambleside) - DWV: Peter + Paul S
 
Mon, June 3, 4-6pm:, 13th & Argyle (Ambleside) - DWV: Peter + Paul S
Sat June 1 9:30-12:30 Civic Plaza North Van
+
Sat June 1 9:30-12:30 Civic Plaza North Van???
Sat June 1 12 pm-2:40 Civic Plaza North Van
+
Sat June 1 12 pm-2:40 Civic Plaza North Van???
 
Thu, Jun 6, 6:15-9am: Lions Gate Hospital - Coastal Health: need 2 people
 
Thu, Jun 6, 6:15-9am: Lions Gate Hospital - Coastal Health: need 2 people
 
DNV & CNV - see Bike Festival above
 
DNV & CNV - see Bike Festival above
Line 37: Line 30:
 
Distribute GBBW posters - libraries, bike stores, coffee shops
 
Distribute GBBW posters - libraries, bike stores, coffee shops
 
Don, Derrick, ???
 
Don, Derrick, ???
  +
 
Blueridge Good Neighbour Day - Sat June 15th
 
Blueridge Good Neighbour Day - Sat June 15th
 
need 4 people for 2 shifts:
 
need 4 people for 2 shifts:
Line 43: Line 37:
 
Asked Brendon to provide eCargo bike
 
Asked Brendon to provide eCargo bike
 
Cargo Bike race - June?
 
Cargo Bike race - June?
  +
 
Shipyards 5th birthday - CNV, Sat July 20th 14:00-20:00
 
Shipyards 5th birthday - CNV, Sat July 20th 14:00-20:00
will need 6 people for 3 shifts: Don, ???
+
will need 6 people for 3 shifts: Don, Paul J, ???
 
Asked Brendon to provide eCargo bike
 
Asked Brendon to provide eCargo bike
   
   
 
City of North Vancouver - Don(temporary)
 
City of North Vancouver - Don(temporary)
  +
No updates
Meeting with Staff
 
Next meeting - TBD
 
Casano-Loutet Overpass
 
Still waiting for MoTI, hope to start this spring.
 
3rd St/Cotton/Lower Level Rd
 
They will look into extending bike lane protection for intersection up to Neptune terminal intersection.
 
Asked them to repaint bikelanes on Lynn Creek Bridge
 
Midtown Connector - HUB top priority
 
High level design work planned for 2024
 
Requested that we be able to provide input on requirements.
 
Central Lonsdale is a Destination, not just a busy road to cross.
 
Upper Levels Greenway
 
1st Stage (2024) will focus on Highway crossing at Lonsdale
 
Next public engagement late in 2024?
 
ITC - Jonathan
 
 
Last Month's meeting was presentation by Translink, but nothing new regarding cycling.
 
Apparently CNV council is discussing the upper level greenway + the lonsdale/hwy overpass later this month. I'm hoping that preliminary designs come to the ITC for input sometime soon.
 
   
   
 
First Nations - Kira
 
First Nations - Kira
  +
First Nations have been contacted but no response as of yet.
Generate summaries of their cycling related goals and then add assessment of how this aligns with our goals. Also how this aligns with neighbouring muni's plans.
 
Develop strategy how to move forward.
 
Plans
 
Squamish Nation
 
Strategic Plan 2022-2026
 
Land Use Plan 2023
 
Tsleil Wauthuth Nation
 
Active Transportation Plan 2023
 
Musquem Indian Band
 
Land Use Plan 2020
 
Improving Active Transportation
 
 
   
 
District of North Vancouver - Duncan/Stephen/Stewart
 
District of North Vancouver - Duncan/Stephen/Stewart

Revision as of 09:14, 3 May 2024

HUB North Shore Committee meeting May 2, 2024

Attending; Paul J (chair), Peter, Fiona, Finn (online) Erika, Mike, Kira


General Agenda additions - none

Events Earth Day event - CNV - was held Sat, April 20th in Moodyville Park. Thanks to Blake, Erika, Finn, Kira, Derrick & Cathy for making this event a success.

1st annual Bike Festival - City hall Plaza, June 1st Sponsored by DNV, CNV, ICBC & North Shore Safety Council yes (need 4 people): Heather, Sophia, Erika 10-12: 12-2pm: Can't: Don, Paul J, Duncan There is confusion as to wether this station is part of GBBW. Paul J has contacted An Hoang for clarification.


Spring Go By Bike Week, June 3-9, 2024. Celebrations stations (2 per station): Mon, June 3, 4-6pm:, 13th & Argyle (Ambleside) - DWV: Peter + Paul S Sat June 1 9:30-12:30 Civic Plaza North Van??? Sat June 1 12 pm-2:40 Civic Plaza North Van??? Thu, Jun 6, 6:15-9am: Lions Gate Hospital - Coastal Health: need 2 people DNV & CNV - see Bike Festival above Asked Brendon to provide eCargo bikes Distribute GBBW posters - libraries, bike stores, coffee shops Don, Derrick, ???

Blueridge Good Neighbour Day - Sat June 15th need 4 people for 2 shifts: yes: Stewart, ??? Can't: Don, Mike Asked Brendon to provide eCargo bike Cargo Bike race - June?

Shipyards 5th birthday - CNV, Sat July 20th 14:00-20:00 will need 6 people for 3 shifts: Don, Paul J, ??? Asked Brendon to provide eCargo bike


City of North Vancouver - Don(temporary) No updates


First Nations - Kira First Nations have been contacted but no response as of yet.

District of North Vancouver - Duncan/Stephen/Stewart Regular Bi-monthly Meeting with Staff took place in early April Projects/sections MSP upgrades moving ahead in 2024 as planned with Translink funding recently secured Main Street - North side construction ongoing and on-track. South side remains an issue. Longer term objective to deal with it but space is problem. Doing some initial review of space and talking to Translink re funding due to sharing with buses. Phibbs Exchange should be complete May. DNV welcomed feedback. Following extensive concerns raised on Hub group email, feedback has been provided, and awaiting response. Longer term plans for greenway/bike route all through Orwell. Further details including timing requested. Spirit Trail East - Staff have been requested to go back to council on May 13th to provide update due to opposition. Planning is pushing ahead. Need to contact staff to see how we can support. Lynn Valley Road - preparing implementation plan for Phase 2 and looking to tie-in stretch by mall. Have translink funding for transit study. Capilano Rd - Ridgewood to Hwy - Developing designs for protected bike lane. Trying to encourage MOTI to deliver their section too. E-cargo bike scheme https://www.dnv.org/streets-transportation/e-cargo-bikes About to go out to tender expect at least 2 bids. Was aiming for June but likely to be a bit later in the summer. Pilot will run for 2 years with 7 stations and likely 9 bikes across two types (box and long tail).


District of West Vancouver - Paul/Peter/Mike 12 April Howe Sound Forum discussion re: a Howe Sound multi-purpose trail

This meeting presented Mayor Sager with an opportunity to follow up with his proposal for a MUP between Horseshoe Bay and Whistler. On behalf of DWV, the mayor hosted this semi-annual forum and arranged for BC Minister of Tourism, Arts and Culture, Lana Popham to attend. The Minister presented her ideas and seeks feedback on the concept of a long-distance (100km+) multi-use trail between Vancouver and Pemberton. She set a goal of compiling options and issues for discussion in July 2024. The forum participants were separated into several round table groups to consider the proposal options and raise questions. The Minister’s proposal was generally well received by the meeting participants, both as a low-carbon tourism initiative and for its economic benefits. The possible trail routes and their likely costs and possible public and private funding sources were discussed. The Mayor of Squamish informed the forum of the advanced work already in place for a trail between Pemberton and Squamish, and the ongoing planning for a link between Squamish and Lions Bay. Several speakers however expressed concern about visitor growth and overuse impacts on indigenous and natural assets. Here is Paul's draft report of the meeting: https://wiki.bikehub.ca/images/a/a5/2024-04-12_Howe_Sound_Forum_Draft_Report.pdf Current Projects from staff's briefing slides to a 7 May Environment Committee meeting

The time of the meeting is 4:30 p.m. and the location is the Cedar Room, 3rd floor of West Vancouver Community Centre - the public can attend. Marine Drive east of Lions Gate Bridge Cycling Link Multi-use pathway on the south side of Marine Drive from Lions Gate Bridge off-ramp to Capilano Road coordinated project with DNV, construction 2024 (pending MoTI permitting) Taylor Way Off-Ramp MUP Multi-use pathway along the westbound Highway 1 ramps at Taylor Way between Hadden Drive and Westcot Road Construction 2025 (pending MoTI permitting) Marine Drive & 31st Street intersection upgrades Full signalization and improvements to pedestrian and bike crossings Connects bike lanes on Marine Drive (26th to 31st Streets) with the uphill Bike lane from 31st Street to Westmount Road Final design phase to be completed this year. DWV Planning Committee

Looking to add people to the Planning Committee https://westvancouver.ca/government-administration/committees-groups/volunteer-board-or-committee Deadline for apps May 31. Ministry of Transportation & Infrastructure - Mike/Don Repeatedly asked HUB's MoTI prime for information on several projects, but no response. List of cycling Gaps in lower mainland region Capilano road underpass design Lynn Valley Rd underpass design Cathy of HUB HQ is organizing meeting with MoTI's AT team, hopefully this month MOTI has asked for an assessment of the performance of their maintenance contractor Miller Capilano Survey will be read aloud for committee members to grade at our May 2/24 meeting. Don Quote "From a cycling perspective this means the highway shoulders from Horseshoe Bay to Capilano road. All road & pedestrian crossing of the highways, Taylor way and the bridges+accesses (on/off ramps)."


Communications & Outreach - Rueben/Paul/Heather let us know if there is something we should communicate about - blocked bike lanes, new infrastructure, etc. Implementation of Strava HUB bike club Twitter (Rueben) Posted update on Orwell Street connection (Phibbs Exchange) North Vancouver Cargo E-bike sharing Current state of Main Street bike lane construction (north side) Facebook(Heather) SPIRIT TRAIL Maplewood to Deep Cove Translinks new Ridelink app Main Street Improvements Slip lane crowd-source Financial Plan - CNV Other(Heather) Hand-out and online info for the Spirit Trail Maplewood to Deep Cove North Shore News New rules mean B.C. drivers must keep further away from cyclists E-scooters legal in North Vancouver for four more years


Schools - Paul Janzen Ride the road course at Ridgeway (2 sessions) and at Carisbrooke.