Line 162: Line 162:
*Lower Lynn - Monthly meeting
*Lower Lynn - Monthly meeting
** ''Mountain Hwy Interchange''
** ''Mountain Hwy Interchange''
*** 4m MUP along westbound Mtn Hwy offramp will have 4 level "refuges" so the hill will be a series of 10m 15% pitches with 2m flats.
*** 4m MUP along the north side westbound Mtn Hwy offramp will have 10 "refuges", so the hill will be a series of 10m 15% pitches with 2m flats (refuge).
** ''Mt Seymour parkway/Keith Interchange''
** ''Mt Seymour parkway/Keith Interchange''
*** bike detour in place until June (to demolish old bridge and complete south side of new one)
*** bike detour in place until June (to demolish old bridge and complete south side of new one)

Revision as of 23:26, 21 March 2021

Starting in April 2021 HUB North Shore Committee regular meetings will change to using abc, still on the first Thursday of every month at 6:30pm - 8:30pm.

Everybody is welcome.

Online conference call at [https:// https:/], It's pretty similar to join.me, but I will start the meeting around 6:15 so people can get connected and try it out.

  • Agenda additions
  • Introductions

Esplanade Complete Street project

  • Mo Bot, Project Manager of Public Realm Infrastructure, for the City of North Vancouver will provide an update on the Esplanade Complete Street project. They are currently working through early design work and planning for Spring engagement – likely beginning in April. Mo will present the current design, share thinking about our trade-offs and choices, and have a discussion with the group.

General

  • Recruiting:
    • DNV Liaisons
    • Vice Chair
    • Wiki-Master


  • Public Input/Consultations:



Events - Fred/Tove

  • Spring Bike2Work Week - May 31 to June 4 -
    • "Knowledge HUBs' instead of Celebration stations


  • Kings Mill Walk master plan
  • City Priority Routes
    • Phase 1
      • 1st Street (pooling areas fixed, paint is coming WHEN?)
      • Casano-Loutet overpass (construction starts in the spring)
      • Jones - ANY UPDATES? Timeline, extents, ...
    • Phase 2
      • Esplanade
      • Midtown Connector to Casano Loutet bridge - 13th to Boulevard then up to 17th? NEXT STEPS?
      • Upper Levels Greenway East
    • Phase 3
      • St. Davids
      • Chesterfield 13th down
      • Upper Levels Greenway West
  • ITC - Dana & Jonathan

District of North Vancouver - Fred/Don

  • Liaisons met a couple times with Ingrid (DNV) and have another meeting scheduled Mar 27?
    • discussed HUB Priorities and 2021 plans
    • Upper LV Road (Phase I) from TC to Peters Road in 2021. Peters to Dempsey planned for 2022 but may be included in Phase I.
    • Upper LVR improvements contingent on obtaining third party infrastructure funding. Assuming funding is successful it means the "DNV will be spending 50% of the transportation budget on active transportation according to Mayor Little."
    • The DNV will be expediting improvements to the Mountain Hwy corridor to Lynn Valley town centre to address cycling impediments. Awaiting details.
    • Liaisons requested road paving schedule, not finalized yet, but Ingrid confirmed that a section of LVR east of Molly Nye and Mount Royal east of Delbrook will be repaved in 2021. Ingrid will share complete schedule when available.

Mtn. Hwy to Peters Road

  • Currently in the design stage
  • HUB Liaisons have been asked to provide input
  • In general terms there will be a protected bike lane on both sides of Lynn Valley Rd as part of phase I. (Mountain Hwy to Peters Rd.)
  • Design looks promising, HUB provided feedback on intersections and signage
  • Will need to make sure that design meshes with plans for LV TC bike plans


Phibbs to Keith

  • Brought up issues with Orwell (poor lane condition). Phibbs will be done before Orwell will be addressed. At this point all that could be done at Orwell at this time would be brush cleaning.
  • Travel by bike or on foot from Keith Rd. bridge to east Seymour via Fern Street Bridge is no more as this bridge has been demolished. The contractor has been slow to open travel over the new overpass connecting with Mt. Seymour Parkway.

Capilano Rd/Highway Underpass MOTI project

  • Discussed, focused on the need to make sure project connects with Hugo Ray bike route
  • Don will forward email with HUB concerns

Other

  • Need to ask about budget for missing Wayfinding signage
  • DNV did not buy bike path sweeper in 2020 due to COVID-19, but not sure if it is in the 2021 budget request.
  • Started discussion of adding protection to bike lanes on Mountain Highway south of the Hwy Overpass
  • Draft designs for a MUP on east and west side of Mountain Hwy north of the overpass.

District of West Vancouver - Paul/Peter/Mike

  • At a 22 February meeting with DWV Engineering and Transportation director, Jenn Moller, and Vanessa Garrett, we learned the following for 2021:
    • Conditional on budget approval, the contract for a Strategic Transportation Study will be awarded and, following internal and external stakeholder engagement, should be completed by the end of the year.
    • Improvement of the Welch St Bridge and its approaches will include some of our recommended detailed design improvements (including dropdown widening and lane-share markings.) but, given the heavy reliance on this
    • A possible ‘mobility recovery pilot’ will be considered (responding in part to our ‘slow street’ expansion proposals), in which the Dept would be receptive to our input and our offer to provide a HUB letter of support to the Mayor and Council should the Dept proceed to present a staff report to Council in the Spring.
  • Other components of M2M discussed at our meeting and which may warrant further discussion in due course included the following:
    • Implementation of an eastbound protected bike lane along Marine Drive from the Lions Gate bridgehead to Capilano Road in collaboration with DNV may take place during the second half of the year, conditional on *Other components of M2M discussed at our meeting and which may warrant further discussion in due course included the following:
    • A bypass to the busy dog-walk access section of Spirit Trail to run from Welch St to 13th St, which would help divert commuters and sports cyclists away from the pedestrian users, but which would depend in part on Park Royal cooperation.
    • Completion of the separated bikeway through Ambleside Waterfront Park requiring closure of Argyle Ave to motor vehicles. We understand this matter may be considered as part of the Ambleside Town Centre Plan. deliberations.
    • In this regard, it was appreciated that staff can provide details of Ambleside parking availability prior to the Grosvenor development, so that we can inform Council on how many more public parking spaces are now available to compensate for the removal of parking places on Argyle Avenue.
  • Lastly, given the extensive mobility-related agenda ahead, their suggestion for Dept staff to meet routinely with HUB on a quarterly basis was much appreciated and fully acceptable. 
  • On 26 February, comments were submitted to the directors of planning and engineering on the Horseshoe Bay Local Area Plan
    • Expressed was our desire for separated bike lanes on Royal Avenue south of Bruce Street connecting to the existing separated bike lane northbound between Bruce and Bay Streets.
    • Also connecting to the existing northbound separated bike lane on Royal Avenue, we would like to see separated east-west bike lanes on Bay Street between Nelson Avenue and the BC ferry terminal building.
  • On 2 March, a letter was sent to the Mayor and Council expressing our concerns about the lack funds being devoted to cycling infrastructure in the 2021 budget which will come up for discussion at Council on 8 March.
  • Preliminary Bikeability Assessment Report for Park Royal - http://wiki.bikehub.ca/northshore/images/8/85/2021-03-03_Preliminary_Bikeability_Assessment_Report_for_Park_Royal.pdf

MOTI - Don/Jonathan

  • Lower Lynn - Monthly meeting
    • Mountain Hwy Interchange
      • 4m MUP along the north side westbound Mtn Hwy offramp will have 10 "refuges", so the hill will be a series of 10m 15% pitches with 2m flats (refuge).
    • Mt Seymour parkway/Keith Interchange
      • bike detour in place until June (to demolish old bridge and complete south side of new one)
      • New 4m wide MUP on side of Mt Seymour pkwy no open, new 3m one on south side will be completed by early June
    • Main-dollarton interchange
      • onramp to IWMB west sidewalk closed until June (detour via east sidewalk)
      • new 4m MUP on south side of main-dollarton will open in June
      • new 4m MUP on north side of main-dollarton should open in July?
    • Phibbs exchange upgrade
      • Construction should should start in late summer


  • BC Economic Recovery funding - for MoTI
    • started in Nov, must be spend by March!
    • HUB provided feedback to design team (Parsons) on near final design of Lynn Valley Rd underpass and Capilano Rd interchange
    • 3 North Shore Projects:
      • Lynn Valley Rd Underpass - Design only (ready to put out to tender) - reviewed 2nd draft
        • have widened bikeway to 2.5m next to 2m pedestrian path, right though underpass
        • cross-ride + crosswalk added to intersection N of overpass
        • on-ramp slip-lane is removed and off-ramp corner sharpened to improve visibility and reduce speeds
      • Capilano Road interchange - Design only (ready to put out to tender) - reviewed 2nd draft
        • They have widened the bikelanes on Capilano Road to 2.5m to allow passing (for much of the distance)
        • Asked for larger waiting spaces at intersection crossings & islands (NB)
        • Will have a separate meeting to discuss repairing & improving connection from North Intersection to North sidewalk and thus Hugo Ray in West van
      • Lion Gate Bridge improvements
        • barriers on both sides of the North end of the bridge have been extended a couple weeks ago.
        • some improved wayfinding signage should be installed on the causeway.


  • Hwy 1 North Shore Corridor Study Lynn Valley to Horseshoe Bay
    • Still waiting for draft report

Communications & Outreach - Heather/Antje/Giacomo/Paul

Planning

  • We are working on coordinating our approach to communications using existing groups.io, Facebook and Twitter
  • Established working tools, What's App and Google Drive to coordinate communications
  • Have identified a volunteer photog/video who will help capture images of the North Shore
  • Looking for people to be models in photoshoots (any volunteers?)
  • Identified top two target groups: Active Seniors and Parents of Young Children - working out how to access these audiences
  • Learning about Instagram and how we might use it to target younger people

Comms Topics Feb/ early March

  • 2020 Year in Review Summary
  • Letter to the Editor, 1st and 2nd Street bikeway
  • Fern Street Detour Route
  • Promote HUB Cargo Bike seminar
  • Promote CNV HUB award
  • New crossing over Mosquito Creek at Evergreen
  • Bafflegate at Keith Road
  • Esplanade complete streets


Developers - Fred/Paul & Peter

  • Currently active:
    • West Van
      • Marine Drive
    • CNV
      • Habourside
    • DNV
      • Maplewood