Difference between revisions of "Meeting Summary: April 9, 2015"

From committees
Jump to navigation Jump to search
imported>Peter Scholefield
imported>Peter Scholefield
 
(One intermediate revision by the same user not shown)
Line 4: Line 4:
 
#* this item took up most of the meeting with discussion about the best bike routes into and through Lyn Valley.
 
#* this item took up most of the meeting with discussion about the best bike routes into and through Lyn Valley.
 
#* routes identified in the Lynn Valley Town Centre plans were discussed as were those routes identified on the bike master plan
 
#* routes identified in the Lynn Valley Town Centre plans were discussed as were those routes identified on the bike master plan
#* there were suggestion of other route to consider, some of them off-street pathways
+
#* there were suggestion of other routes to consider, some of them off-street pathways
 
#* It was agreed that there wasn't too much we could do about the Lynn Valley Town Centre routes as we have already made considerable input to the plans
 
#* It was agreed that there wasn't too much we could do about the Lynn Valley Town Centre routes as we have already made considerable input to the plans
 
#* It was decided that it would be a good idea to arrange a group ride so that we could become more familiar with some of the route options that were raised
 
#* It was decided that it would be a good idea to arrange a group ride so that we could become more familiar with some of the route options that were raised
Line 11: Line 11:
 
# North Shore Committee chair position open
 
# North Shore Committee chair position open
 
#* Antje formally announced that she was stepping down as Committee chair after this meeting
 
#* Antje formally announced that she was stepping down as Committee chair after this meeting
* Peter thanked Antje for the excellent work she had done as chair and the attendees responded with an an applause
+
#* Peter thanked Antje for the excellent work she had done as chair and the attendees responded with an an applause
* Peter said that he would chair the next meeting at which time nominations for a new chair would be accepted
+
#* Peter said that he would chair the next meeting on 14 May at which time nominations for a new chair would be accepted
 
# Bike BC provincial funding for cycling infrastructure
 
# Bike BC provincial funding for cycling infrastructure
 
#*attendees were encouraged to urge local municipal governments to take advantage of Bike BC funding
 
#*attendees were encouraged to urge local municipal governments to take advantage of Bike BC funding
# HUB library event March 16 recap (Fiona - 2min)-
+
# HUB library event March 16 recap
  +
#*Fiona is suggesting on 25 May we organize a similar event that was held last year to celebrate Canada Bike Day in the North Van City square
# West Van cycling infrastruture issues (Peter 10 min):
+
# West Van cycling infrastructure issues
* Hwy 1 north side paved shoulder west of Capilano River to 3rd Street
+
#* Hwy 1 north side paved shoulder west of Capilano River to 3rd Street needs improvement now that the path down to Keith road has been improved with a packed gravel surface
* War Dance Bridge
 
  +
#* War Dance Bridge - Park Royal is still looking for another $500,000 to match their $500,000 to comppmlet the palnned project
* 1300 block Marine Drive redevelopment
 
  +
#* 1300 block Marine Drive redevelopment - the 1300 block Bellevue bike route will be closed into June while construction begin on the Grosvenor 1300 block redevelopment project
* 1100 block Keith Road
 
  +
#* 1100 block Keith Road - an open house was held in March concerning the proposed sidewalk on the south side but we would like a bike lane on the north side
* wayfinding signage
 
  +
#* wayfinding signage - District engineer John Calimente has been consulting Antje and Peter about suggestion to install wayfinding signage on West Van bike routess

Latest revision as of 23:19, 11 May 2015

  1. Attendance: Antje, Peter, Tony, Dennis, Nelson, Don, Rob, Erika, Giacomo, Sheldon, Andrew, Martyn, Fiona, Nick
  2. Lynn Valley bike network
    • this item took up most of the meeting with discussion about the best bike routes into and through Lyn Valley.
    • routes identified in the Lynn Valley Town Centre plans were discussed as were those routes identified on the bike master plan
    • there were suggestion of other routes to consider, some of them off-street pathways
    • It was agreed that there wasn't too much we could do about the Lynn Valley Town Centre routes as we have already made considerable input to the plans
    • It was decided that it would be a good idea to arrange a group ride so that we could become more familiar with some of the route options that were raised
  3. Transit plebiscite - North Shore action
    • flyers promoting a yes vote were distributed at the Lonsdale Quay on 30 March and at the Phibbs Exchange on 2 April
  4. North Shore Committee chair position open
    • Antje formally announced that she was stepping down as Committee chair after this meeting
    • Peter thanked Antje for the excellent work she had done as chair and the attendees responded with an an applause
    • Peter said that he would chair the next meeting on 14 May at which time nominations for a new chair would be accepted
  5. Bike BC provincial funding for cycling infrastructure
    • attendees were encouraged to urge local municipal governments to take advantage of Bike BC funding
  6. HUB library event March 16 recap
    • Fiona is suggesting on 25 May we organize a similar event that was held last year to celebrate Canada Bike Day in the North Van City square
  7. West Van cycling infrastructure issues
    • Hwy 1 north side paved shoulder west of Capilano River to 3rd Street needs improvement now that the path down to Keith road has been improved with a packed gravel surface
    • War Dance Bridge - Park Royal is still looking for another $500,000 to match their $500,000 to comppmlet the palnned project
    • 1300 block Marine Drive redevelopment - the 1300 block Bellevue bike route will be closed into June while construction begin on the Grosvenor 1300 block redevelopment project
    • 1100 block Keith Road - an open house was held in March concerning the proposed sidewalk on the south side but we would like a bike lane on the north side
    • wayfinding signage - District engineer John Calimente has been consulting Antje and Peter about suggestion to install wayfinding signage on West Van bike routess