Meeting Summary: September 11, 2014

From committees
Revision as of 10:58, 12 September 2014 by imported>Peter Scholefield
Jump to navigation Jump to search
1. Mark, Sybil. Antje, Nelson, Fiona Brian

2. libray update Fiona 3. Announcements – Teloworks AAA, tourism. SFU woodwards Gil Penalosa speeks in evening 1900 – 8-80 cities ticket online -Low level open in October -Dlolarton wider than bridge sidewalk - 4. 1.8m sidewalk, 1.5m bike lane on each side of bridge – reommend changed approach with plastic bollards – bridge at crown street as well which will lead to Spirit Trail. - apsend a Hub letter supporting bridge plan and ask for continued separated bike lanes on the approached as far as possible. 5. Phibbs interchange – RFP Sep 15 for design -want HUB input to the design 6. Forbes 3rd st intersection – Brian has drafted up an assessment letter with maps and photos 7. hwy 1 cap bridge assessment ride – Darlene rides it a lot – ride set for early October 8. Jones: Heather wrote a letter but construction of the multi-purpose path on the west side is under construction. 9. BWW- John henry tent Cobbs provided breads 27-31 October- Brian will help orgnize a station at the 2nd narrows – Fiona, Peter and Dennis will help as well as our event organizers library event – hub presentation next year during spring break

  1. Attendance: Antje, Peter, Mark, Sybille, Brian, Fiona
  2. Review of agenda, additional agenda items (5 min)
  3. Announcements (all 5 mins)
  4. New Keith Bridge Drawing Review (Brian - 15 min)
  5. New Phibbs Exchange, cycling access (Antje - 5 min)
  6. 3rd Street/Forbes assessment ride (Brian - 10 min)
  7. West Vancouver Highway 1 north side assessment ride (Antje - 5 min)
  8. New Jones AAA bike route (Heather - 5 min)
  9. Fall Bike to Work Week (5 min)
  10. Clyde-Keith Traffic Calming project in West Vancouver (Peter - 5 min)
  11. West Van cycling infrastructure update
    • Wardance Bridge delayed to 2015
    • Wayfinding signage on all of Spirit Trail very soon
    • Widen pathway this fall on Pacific Capilano Trail from under Wardance bridge north to Marine Drive
    • Inglewood and 3rd design approved and will start construction in a few weeks
    • Spirit Trail west from Eagleridge Drive to Eagleridge School planned for late September through November